Document-based historical archive

1992 System-Development Sequence

The 1992 records raise a timing question for any claim that the Reed source was already a completed regulated system component in 1990.

Why 1992 matters

A proposed system, planned system, or system under discussion is not the same thing as a completed operational system. The 1992 records should be compared against any claim that the Reed well was already part of a completed regulated system in 1990.

Key 1992 records

DateRecord / eventWhy it matters
February 2, 1992Water tank placement discussion / planning recordA tank-location discussion supports a planning or unresolved-infrastructure condition. It does not, by itself, prove a completed system existed in 1990.
June 11, 1992Lynch invoice / pump, pipeline, electrical, or connection-related workThis record is central because it appears to document later installation or connection activity after the claimed 1990 system date.
September 11, 1992Luschen Grant of Easement involving APN 571-030-039 / tank parcel accessIf access or authority involving the tank parcel was not signed until September 11, 1992, that raises a timing question about pre-existing legal access or operating authority.

Timing question

What record shows that the Reed well was permitted, connected, operational, and lawfully incorporated into the regulated system in 1990, if available records show tank-location planning, installation/connection activity, and easement/access documentation occurring in 1992?